Edinprotechnologies Interview Question
HR ExecutivesCountry: India
Interview Type: Written Test
is a comprehensive book on getting a job at a top tech company, while focuses on dev interviews and does this for PMs.
CareerCup's interview videos give you a real-life look at technical interviews. In these unscripted videos, watch how other candidates handle tough questions and how the interviewer thinks about their performance.
Most engineers make critical mistakes on their resumes -- we can fix your resume with our custom resume review service. And, we use fellow engineers as our resume reviewers, so you can be sure that we "get" what you're saying.
Our Mock Interviews will be conducted "in character" just like a real interview, and can focus on whatever topics you want. All our interviewers have worked for Microsoft, Google or Amazon, you know you'll get a true-to-life experience.
Let 240W be the amount of work to be done, then per day
- Maego November 03, 2021Amount of work done by A = 240W/60 = 4W,
Amount of work done by B = 240W/40 = 6W
After 12 days, amount of work done by both
= (4W + 6W) * 12 = 120W
Remaining amount of work to be done
= 240W - 120W = 120W
Number of days to complete the remaining work by B
= 120W/6W = 20